32° East is a home for creation, experimentation and critical thinking through contemporary art. Since 2011, we’ve expanded possibilities for art making in Uganda through our residencies, resource centre and public programming.
In 2021 after a long journey of fundraising, plot searching, design changing and more, we finally broke ground on the first ever purpose built art centre in Kampala. We have split the design and construction of the centre into two phases, to make the most of the funding that we have been able to raise thus far. Phase I was completed in January 2023.
Through support from incredible donors, significant grants from the Sigrid Rausing Trust, DOEN Foundation, Outset Contemporary Art Fund, and the African Arts Trust, an in-kind contribution from Roofings Group plus pro-bono architectural services from New Makers Bureau, phase 1 will consist of 3 artists’ studios, a library, and a café. But this is just the beginning! To celebrate this moment and to launch fundraising drive for phase 2, we held a crowdfunding campaign #32BreaksGround, which brought an additional $96,000 towards the project. This phase will include 3 more studios, a gallery and walled garden, workshop space, and shops. Please get involved and join hundreds of supporters in helping bring our dream to life!
- 2nd Feb 2023 – Phase 1 is Complete! #ThisIs32 #32Phase1DoneAlex Lyons2023-02-17T14:51:43+03:00
2nd Feb 2023 – Phase 1 is Complete! #ThisIs32 #32Phase1Done
- 12th Jan 2023 – The final paint layers in the studios are up & dry!Alex Lyons2023-02-17T14:37:53+03:00
12th Jan 2023 – The final paint layers in the studios are up & dry!
- 15th Dec 2022 – Placing of the clay tile drops are almost complete!Alex Lyons2023-02-17T14:16:38+03:00
15th Dec 2022 – Placing of the clay tile drops are almost complete!
- 8th Dec 2022 – They’ve began cutting the stones for the walkways!Alex Lyons2023-02-17T14:07:56+03:00
8th Dec 2022 – They’ve began cutting the stones for the walkways!
- 1st Dec 2022 – Our last site tour of the year, at our End of Year Meet-Up!Alex Lyons2023-02-17T13:42:58+03:00
1st Dec 2022 – Our last site tour of the year, at our End of Year Meet-Up!
- 24th Nov 2022 – A sample strip light has been put into one of the studios!Alex Lyons2023-02-17T13:25:03+03:00
24th Nov 2022 – A sample strip light has been put into one of the studios!
- 10th Nov 2023 – They’ve begun the tile detail on the cafe!Alex Lyons2023-02-17T13:06:38+03:00
10th Nov 2023 – They’ve begun the tile detail on the cafe!
- 3rd Nov 2022 – Started painting the lintel with red oxide!Alex Lyons2023-02-17T12:58:31+03:00
3rd Nov 2022 – Started painting the lintel with red oxide!
- 27th Oct 2022 – Our October Construction Update videoAlex Lyons2023-02-17T12:35:24+03:00
27th Oct 2022 – Our October Construction Update video
- 20th Oct 2022 – The electrical wiring has been put in!Alex Lyons2023-02-17T12:16:16+03:00
20th Oct 2022 – The electrical wiring has been put in!
- 13 Oct 2022 – The plastering for the studios has began!Alex Lyons2023-02-17T12:16:51+03:00
13 Oct 2022 – The plastering for the studios has began!
- 6th Oct 2022 -The window frames have arrived!Alex Lyons2023-02-17T12:19:41+03:00
6th Oct 2022 -The window frames have arrived!
- 29th Sept 2022 – Our September Construction Update videoAlex Lyons2023-02-17T12:27:52+03:00
29th Sept 2022 – Our September Construction Update video
- 22nd Sept 2022 – The retaining wall is almost complete!Alex Lyons2023-02-17T12:29:06+03:00
22nd Sept 2022 – The retaining wall is almost complete!
- Sept 15th 2022 – Preparations are underway for the roof shingles!Alex Lyons2023-02-17T12:28:37+03:00
Sept 15th 2022 – Preparations are underway for the roof shingles!
- 1st Sept 2022 – Milestone 5 has been achieved!Alex Lyons2022-09-02T15:30:25+03:00
1st Sept 2022 – Milestone 5 has been achieved!
- Aug 25th 2022 – August #ConstructionUpdate video is here!Alex Lyons2022-09-02T15:24:24+03:00
Aug 25th 2022 – August #ConstructionUpdate video is here!
- Aug 18th 2022 – We show our board progress in person!Alex Lyons2022-09-02T15:33:12+03:00
Aug 18th 2022 – We show our board progress in person!
- 28th July 2022 – July’s #ConstructionUpdate video is here!Alex Lyons2022-07-29T13:56:34+03:00
28th July 2022 – July’s #ConstructionUpdate video is here!
- 21st July 2022 – The column and roof work bring our structure to new heightsAlex Lyons2022-07-29T13:49:50+03:00
21st July 2022 – The column and roof work bring our structure to new heights
- 14th July 2022 – Our café is looking extra fresh now that the wooden form-workAlex Lyons2022-07-29T13:30:09+03:00
14th July 2022 – Our café is looking extra fresh now that the wooden form-work
- 30th June 2022 – Highlighting our studio’s successful ring beam installationAlex Lyons2022-07-29T13:59:45+03:00
30th June 2022 – Highlighting our studio’s successful ring beam installation
- 15th June 2022 – We hosted the ‘Artachat x Localtalks’ in our future Cafe!Alex Lyons2022-06-20T15:33:09+03:00
15th June 2022 – We hosted the ‘Artachat x Localtalks’ in our future Cafe!
- 14th June 2022 – Pictures showing with how far we’ve have come.Alex Lyons2022-06-20T15:31:19+03:00
14th June 2022 – Pictures showing with how far we’ve have come.
- June 10th 2022 – Our contractors, Localworks, working on a cavityAlex Lyons2022-06-20T15:31:44+03:00
June 10th 2022 – Our contractors, Localworks, working on a cavity
- 26th May 2022 – For this month, our café is the star of the show!Alex Lyons2022-06-20T12:52:44+03:00
26th May 2022 – For this month, our café is the star of the show!
- 19th May 2022 – The sample wall is almost complete!Alex Lyons2022-05-27T15:56:59+03:00
19th May 2022 – The sample wall is almost complete!
- 12 May 2022 – Studio walls are done & the rammed earth for the cafe has begun.Alex Lyons2022-05-17T13:08:19+03:00
12 May 2022 – Studio walls are done & the rammed earth for the cafe has begun.
- 5th May 2022 – Highlights from the Members Meetup + Construction UpdateAlex Lyons2022-05-11T15:08:41+03:00
5th May 2022 – Highlights from the Members Meetup + Construction Update
- 28th April 2022 – We hit the halfway mark on Phase 1!Alex Lyons2022-05-11T14:40:00+03:00
28th April 2022 – We hit the halfway mark on Phase 1!
- 21st April 2022 – The studio walls have reached ring beam level!Alex Lyons2022-05-11T14:11:00+03:00
21st April 2022 – The studio walls have reached ring beam level!
- 14th April 2022 – Work has begun on the final section of the studios’ rammed earth wallAlex Lyons2022-04-14T14:27:32+03:00
14th April 2022 – Work has begun on the final section of the studios’ rammed earth wall
- 7th April 2022 – Members’ meet-up and community site tours!Alex Lyons2022-04-12T15:18:28+03:00
7th April 2022 – Members’ meet-up and community site tours!
- 31st Mar 2022 – Check out the progress on the walls!Alex Lyons2022-04-12T14:57:03+03:00
31st Mar 2022 – Check out the progress on the walls!
- 24th Mar 2022 – Spotlight on the beautiful compressed earth blocks for our new studiosAlex Lyons2022-04-14T14:14:37+03:00
24th Mar 2022 – Spotlight on the beautiful compressed earth blocks for our new studios
- 17th Mar 2022 – The first lift (or level) of rammed earth for studio walls is completeAlex Lyons2022-04-14T13:31:03+03:00
17th Mar 2022 – The first lift (or level) of rammed earth for studio walls is complete
- 10th Mar 2022 – The ramming of the earth has begun!Alex Lyons2022-03-25T15:25:29+03:00
10th Mar 2022 – The ramming of the earth has begun!
- 24th Feb 2022 – A summary of what’s been happening this weekAlex Lyons2022-04-14T14:12:02+03:00
24th Feb 2022 – A summary of what’s been happening this week
- 17th Feb 2022 – The stone wall is done and so is the concrete kicker!Alex Lyons2022-04-14T12:41:00+03:00
17th Feb 2022 – The stone wall is done and so is the concrete kicker!
- 10th Feb 2022 -The stone portion of the wall is almost completeAlex Lyons2022-04-14T13:19:09+03:00
10th Feb 2022 -The stone portion of the wall is almost complete
- 27th Jan 2022 – 4,600 compressed earth blocks down 30,400 to go!Alex Lyons2022-03-25T12:45:14+03:00
27th Jan 2022 – 4,600 compressed earth blocks down 30,400 to go!
- 20th Jan 2022 – Earth construction as a model for alternative building techniquesAlex Lyons2022-03-18T14:41:10+03:00
20th Jan 2022 – Earth construction as a model for alternative building techniques
- 13th Jan 2022 – Here’s a look back at how far we’ve come!Alex Lyons2022-03-18T14:34:48+03:00
13th Jan 2022 – Here’s a look back at how far we’ve come!
- 16th Dec 2021 – The foundation for Phase One will be completedAlex Lyons2022-03-18T14:26:30+03:00
16th Dec 2021 – The foundation for Phase One will be completed
- 25th Nov 2021 – Getting closer to completing the building’s foundation!Alex Lyons2022-03-18T14:16:31+03:00
25th Nov 2021 – Getting closer to completing the building’s foundation!
- 18th Nov 2021 – Front row seat to our experimental construction process!Alex Lyons2022-03-18T14:04:43+03:00
18th Nov 2021 – Front row seat to our experimental construction process!
- 11th Nov 2021 – Finalising demolition, excavating the earth for the buildingAlex Lyons2022-03-18T14:03:58+03:00
11th Nov 2021 – Finalising demolition, excavating the earth for the building
- 28th Oct 2021 – The long awaited Demolition Day!Alex Lyons2022-02-25T13:17:11+03:00
28th Oct 2021 – The long awaited Demolition Day!
- 7th Oct 2021 – A live demo of adding rammed earth layers to the sample wallAlex Lyons2022-03-25T12:35:04+03:00
7th Oct 2021 – A live demo of adding rammed earth layers to the sample wall
- 30th Sept 2021 – Update from Andrew Kaggwa, the CarpenterAlex Lyons2022-02-25T15:48:25+03:00
30th Sept 2021 – Update from Andrew Kaggwa, the Carpenter
- 23rd Sept 2021 – The making of the brick patterns for the buildingAlex Lyons2022-02-25T16:18:40+03:00
23rd Sept 2021 – The making of the brick patterns for the building
- 16th Sept 2021 – Rammed Earth Wall ConstructionAlex Lyons2022-02-25T16:04:59+03:00
16th Sept 2021 – Rammed Earth Wall Construction
- 9th Sept 2021 – Update from our Site EngineerAlex Lyons2022-02-25T15:29:57+03:00
9th Sept 2021 – Update from our Site Engineer
- 2nd Sept 2021 – Step by step process of making compressed earth blocksAlex Lyons2022-02-25T15:12:03+03:00
2nd Sept 2021 – Step by step process of making compressed earth blocks
- 25th Aug 2021 – We built a sample wall on the siteAlex Lyons2022-02-25T13:22:17+03:00
25th Aug 2021 – We built a sample wall on the site
- 19th Aug 2021 – Update from the Assistant ArchitectAlex Lyons2022-02-25T13:12:57+03:00
19th Aug 2021 – Update from the Assistant Architect
- 12th Aug 2021 – Walkthrough from the site managerAlex Lyons2022-02-25T12:40:52+03:00
12th Aug 2021 – Walkthrough from the site manager
- 5th Aug 2021 – The Team learns Health and Safety MeasuresAlex Lyons2022-02-25T13:20:00+03:00
5th Aug 2021 – The Team learns Health and Safety Measures
- 25th July 2021 – Update from Our Construction ManagerAlex Lyons2022-02-25T13:10:35+03:00
25th July 2021 – Update from Our Construction Manager
Our Project Partners
Expanded Resources for the new 32° East
Six artists’ studios
Increasing our current capacity by 100%. We will have three studios dedicated to our residency programme and then have three additional studios that we would lease out to local artists who are more established in their practice and wish to be surrounded by a community of artists who give additional inspiration, feedback, and possible collaboration opportunities.
.
.
A well resourced learning centre and library
To house 32° East’s extensive art library. It will also offer free computer and WI-FI access and an editing suite for digital artists, filmmakers and sound designers. We also have a number of digital toolkits that offer tutorials and templates on writing artist statements, exhibition reviews and applications. We will also have more space to host skills-based workshops, and be able to better accommodate international arts professionals from different contexts who can share alternative practices
A purpose-built public art gallery
To present a rolling programme of free, local and international exhibitions. This gallery will especially highlight non-commercial, more experimental art to serve as a well-resourced space for more adventurous work. It allows us to not only give space to emerging artists to help them find their voice and an audience, but also gives space to emerging curators to do the same.
Accommodation for visiting artists
To improve our facilities for artists and reduce costs. Up to this point, we have hosted creative professionals from over 20 countries but have spent thousands of pounds on external accommodation. This has also meant that we have been unable to host as many regional and international artists which is a severe limitation. When we are not hosting artists, the rooms will be available for short term stays providing revenue for our operations.
Café and art shop
To bring in regular income and reduce our reliance on donor funding. The café will welcome new audiences who may otherwise never visit an art centre and will promote a sustainable ethos by using fresh produce from our on-site garden. We also hope to invite chefs-in-residence from our network, extending international exchange and cross-cultural collaboration beyond the studios. The art shop aims to be a convenient and quality resource for artists who can now go to one place for canvas, brushes, paints etc.
Supporters